Poultry project timeline generator.
An indicative phased schedule for commercial poultry projects. Adjust project type, region, capacity and target dates — the tool re-computes phases using deterministic rules based on typical projects. Not a contractual schedule.
Inputs
Planning estimate only. Not a contractual schedule. Actual durations depend on suppliers, permitting, financing, weather and site conditions.
Indicative timeline
Target window is 52 weeks — ~9 weeks shorter than typical for this scope. Consider phasing, pre-ordering long-lead items or parallelising civil works with manufacturing.
- Phase 1Feasibility & site survey3 weeks · 09 Sept 2026 → 30 Sept 2026
Land, water, power, biosecurity buffer, market study.
- Phase 2Engineering & design4 weeks · 30 Sept 2026 → 28 Oct 2026
House layout, ventilation sizing, utilities, permits.
- Phase 3Supplier RFQ & selection6 weeks · 28 Oct 2026 → 09 Dec 2026
Structured RFQ, shortlist, factory references, contract.
- Phase 4Financing preparationparallel track8 weeks · 09 Sept 2026 → 04 Nov 2026
Bankable pack, ECA / leasing / DFI submission (parallel).
- Phase 5Manufacturing14 weeks · 09 Dec 2026 → 17 Mar 2027
Equipment fabrication and factory acceptance test (FAT).
- Phase 6Shipping & customs7 weeks · 17 Mar 2027 → 05 May 2027
Ocean freight, port clearance, inland transport.
- Phase 7Site preparation & civil13 weeks · 05 May 2027 → 04 Aug 2027
Earthworks, foundations, structure, roads, fencing.
- Phase 8Installation7 weeks · 04 Aug 2027 → 22 Sept 2027
Mechanical, electrical, ventilation, feed & water lines.
- Phase 9Testing & commissioning (SAT)3 weeks · 22 Sept 2027 → 13 Oct 2027
Site acceptance test, controls tuning, staff training.