Poultry project timeline generator.
An indicative phased schedule for commercial poultry projects. Adjust project type, region, capacity and target dates — the tool re-computes phases using deterministic rules based on typical projects. Not a contractual schedule.
Inputs
Planning estimate only. Not a contractual schedule. Actual durations depend on suppliers, permitting, financing, weather and site conditions.
Indicative timeline
Target window is 52 weeks — ~9 weeks shorter than typical for this scope. Consider phasing, pre-ordering long-lead items or parallelising civil works with manufacturing.
- Phase 1Feasibility & site survey3 weeks · 26 Jul 2026 → 16 Aug 2026
Land, water, power, biosecurity buffer, market study.
- Phase 2Engineering & design4 weeks · 16 Aug 2026 → 13 Sept 2026
House layout, ventilation sizing, utilities, permits.
- Phase 3Supplier RFQ & selection6 weeks · 13 Sept 2026 → 25 Oct 2026
Structured RFQ, shortlist, factory references, contract.
- Phase 4Financing preparationparallel track8 weeks · 26 Jul 2026 → 20 Sept 2026
Bankable pack, ECA / leasing / DFI submission (parallel).
- Phase 5Manufacturing14 weeks · 25 Oct 2026 → 31 Jan 2027
Equipment fabrication and factory acceptance test (FAT).
- Phase 6Shipping & customs7 weeks · 31 Jan 2027 → 21 Mar 2027
Ocean freight, port clearance, inland transport.
- Phase 7Site preparation & civil13 weeks · 21 Mar 2027 → 20 Jun 2027
Earthworks, foundations, structure, roads, fencing.
- Phase 8Installation7 weeks · 20 Jun 2027 → 08 Aug 2027
Mechanical, electrical, ventilation, feed & water lines.
- Phase 9Testing & commissioning (SAT)3 weeks · 08 Aug 2027 → 29 Aug 2027
Site acceptance test, controls tuning, staff training.