15 common exclusions in turnkey feed plant quotations

Short answer

Proposals labelled turnkey commonly exclude: civil works and foundations; the building; site preparation and access roads; the electrical supply and transformer; the boiler and fuel system; water supply and treatment; compressed air; backup power; dust-control ducting outside the machine scope; fire detection and suppression; the laboratory; weighbridge; permits and local code compliance; import duties and local transport; and the initial spare-part package. Turnkey is a contract definition, not a standard scope — the exclusions list is the only reliable description of what you are buying.

The word turnkey carries no fixed meaning across suppliers or jurisdictions. Two turnkey proposals can differ by a substantial share of total project cost while both being accurate.

Compare feed mill quotations on one scope

Frequently excluded

  • Civil works, foundations, pits and drainage
  • Building envelope and internal finishes
  • Site preparation, access roads and fencing
  • Electrical supply, transformer and MV works
  • Boiler, fuel storage and steam distribution
  • Water supply, storage and treatment
  • Compressed air generation and distribution
  • Backup generator and changeover
  • Dust-control ducting and explosion venting beyond machine limits
  • Fire detection, suppression and insurance-driven requirements
  • Laboratory equipment and consumables
  • Weighbridge and yard infrastructure
  • Permits, statutory approvals and third-party inspection
  • Import duties, customs clearance and inland transport
  • Commissioning and first-year spare parts

How to close the gap

  • Issue the exclusions list as an RFQ attachment and ask suppliers to mark each line in or out
  • Require a price for every line marked out, or a written statement that the buyer must arrange it
  • Assign a local budget figure to every buyer-side line before comparing totals
  • Recheck the schedule: buyer-side scope is the most common source of delay

Questions buyers ask

What should be included in a true turnkey feed mill price?
A genuinely complete turnkey price covers process equipment, steel structure, electrical installation and automation, installation labour, commissioning, training, documentation and a plant-level performance guarantee, and states clearly whether civil works, the building, the electrical supply, the boiler and utilities are inside or outside. Anything not named is outside.
Can I ask a supplier to take over an excluded line?
Usually yes, priced as an addition. Doing it during the RFQ stage is far cheaper than doing it as a change order after signature.

Continue the decision

Compare feed mill quotations on one scope

Write the requirement once and send the same document to every supplier you are considering, including one you already prefer. FeedMatch sells nothing and takes no part in the contract.

Compare feed mill quotations on one scope

Scope and neutrality

  • FeedMatch Group is an independent, supplier-neutral procurement platform. It does not manufacture, install or commission feed-processing equipment and is not an EPC contractor.
  • FeedMatch does not sell feed, ingredients, premixes or additives and does not act as a trader.
  • FeedMatch is not a bank, lender, credit provider or financial adviser. Financing, where relevant, is arranged by independent third parties.
  • Calculator outputs and planning ranges on this site are indicative inputs for your own evaluation, not quotations, nutritional advice or performance guarantees.
Get a Free QuoteExplore Financing