요구사항 정의 방법
- Convert every offer to landed cost per tonne at your plant gate before comparing anything.
- Fix the quantity tolerance and who exercises it (typically ±5% or ±10% at seller's option).
- Decide where quality and weight are final, and appoint the surveyor in the contract by name or standing.
- Match the payment instrument to counterparty risk: LC at sight, CAD, or open account for established relationships.
- Confirm discharge capability — draft, berth availability, silo intake rate and free storage days.
중요한 규격
| 항목 | 일반 요구값 | 구매자에게 중요한 이유 |
|---|---|---|
| Landed cost per tonne | All-in at plant gate | The only comparable number across FOB, CFR and DAP offers. |
| Quantity tolerance | ±5% or ±10% | Determines exposure if the market moves between contract and shipment. |
| Laytime and demurrage rate | Stated days and USD/day | One of the largest avoidable cost lines in bulk trade. |
| Quality determination point | Load port / discharge | Defines who carries in-transit deterioration. |
| Sampling protocol | Composite, three-way split | Makes any subsequent claim defensible. |
| Payment instrument | LC / CAD / open account | Balances price against counterparty risk. |
| Force majeure and washout terms | Explicit, priced | Determines cost of a failed shipment in a volatile market. |
- — Feed-safety certification of the producing plant (GMP+, FAMI-QS, FSSC 22000 as applicable)
- — Vessel or container food/feed-grade suitability and previous-cargo declaration
- — Fumigation certificate and phytosanitary certificate where required
- — Certificate of origin for tariff treatment and trade-agreement claims
- — Sanctions and counterparty screening documentation retained on file
- — Independent surveyor sampling, weight and quality report at load and discharge
- — Full contaminant panel appropriate to the ingredient and origin
- — Hold and hatch cleanliness inspection report before loading
- — Draft survey or weighbridge certificate supporting settlement weight
- — Retained sealed samples held by buyer, seller and an umpire laboratory
- — Bulk vessel for full or part cargoes where intake and storage allow
- — Container bulk liners for 20–25 tonne parcels and smaller markets
- — Break-bulk bagged cargo where discharge infrastructure is limited
- — Confirm liner specification, sealing and marking before loading
- — Incoterms 2020 selection drives insurance, risk transfer and demurrage exposure — choose deliberately
- — Confirm berth, draft restriction and discharge rate before fixing the vessel
- — Track free time at port and pre-book inland haulage to avoid detention
- — Insure at 110% CIF value with cover matching the real transit risks
- — Verify silo and warehouse capacity against arrival schedule before the vessel sails
- — Segregate lots so quality claims can be traced to a specific shipment
- — Monitor temperature and moisture in bulk piles on a fixed schedule
- — Reconcile received, stored and consumed tonnage monthly to detect shrinkage early
구매 리스크
통제 방안: Realistic laytime negotiated against your actual intake rate, plus pre-booked haulage and storage.
통제 방안: Contracted independent surveyor, composite sampling and a three-way sealed split.
통제 방안: Performance security or LC, split shipments with new counterparties, and documented sanctions screening.
통제 방안: Hedge or contract in the currency of your revenue where possible.
통제 방안: Arrival window clause tied to your silo plan, with staged discharge or bonded storage arranged in advance.
- — Comparing an FOB offer with a DAP offer without building landed cost
- — Accepting quality final at load port while paying against arrival documents
- — Underestimating laytime and discovering demurrage after the fact
- — Leaving the surveyor appointment to the seller
- — Ignoring the tolerance clause and being surprised by 10% more cargo in a falling market
자주 묻는 질문
Which Incoterm should I use?
Is a letter of credit always worth it?
Who should appoint the surveyor?
How do I compare offers fairly?
Most import losses are documentation and timing losses, not quality losses. This checklist covers the commercial and regulatory chain from contract to plant gate.
Your next step, by buying intent
Pick the lane that matches where you are in the purchase — each link goes to the exact tool or page for that step.
What exactly am I buying?
How much, and at what landed cost?
Is this supplier and lot acceptable?
기술 규격과 시험 용어는 국제 계약 및 인증서 표기에 따라 영문으로 표시됩니다.
