The eight phases of a turnkey mill project
Phase 1
Basic and detailed engineering
Typical duration: 6–12 weeks · Starts the critical path — nothing else can be released before it
- —Process flow diagram, mass balance and capacity confirmation per product
- —Layout, silo arrangement, equipment list and motor list
- —Civil loads, foundation drawings and building interfaces
- —Electrical single line, control philosophy and instrument list
Schedule risk: Late nutritionist or product-range changes force re-engineering and push every later phase.
Phase 2
Civil works and building
Typical duration: 12–24 weeks · Runs in parallel with equipment manufacturing
- —Site preparation, piling where ground conditions require it
- —Foundations for tower, silos, boiler house and load-out
- —Building structure, cladding, floors and drainage
- —Power supply, transformer pad, water, steam and effluent connections
Schedule risk: Civil works is usually the phase most exposed to weather, permits and local contractor capacity. It is the second most common cause of a late handover after late engineering.
Phase 3
Equipment manufacturing
Typical duration: 14–26 weeks · In parallel with civil works
- —Main process machines: grinder, mixer, conditioner, pellet mill or extruder, cooler
- —Silos, conveyors, elevators, aspiration and dust filters
- —Electrical panels, MCC and automation hardware
- —Factory acceptance tests where agreed in the contract
Schedule risk: Long-lead items (extruder, boiler, main motors, MCC) set the date. Confirm lead times per item in the quotation, not as one average.
Phase 4
Shipping, customs and site delivery
Typical duration: 4–10 weeks · After manufacturing, before installation
- —Packing list, container or breakbulk planning and Incoterm responsibilities
- —Customs clearance, duty and import permits
- —Inland transport, crane availability and lay-down area
Schedule risk: Duty classification and clearance delays sit outside the supplier's scope in most contracts — check who carries that risk before signature.
Phase 5
Mechanical and electrical installation
Typical duration: 8–16 weeks · Starts when civils are released and the first shipment lands
- —Steel structure, silos and tower erection
- —Machine setting, alignment, conveyors and ducting
- —Cabling, panels, field instruments and earthing
- —Steam, compressed air and fire and explosion safety systems
Schedule risk: Installation cannot start on a partially released building. A civil handover certificate per area keeps the erection crew productive.
Phase 6
Automation and control
Typical duration: 4–8 weeks, overlapping installation · Software in parallel, loop checks after cabling
- —PLC and SCADA configuration, recipe and batching software
- —Weighing calibration and dosing tolerance verification
- —Traceability, batch records and ERP interface
- —Loop checks, interlocks and safety logic testing
Schedule risk: Recipe and traceability requirements are often specified late. Agree the data model and who owns the source code and licences in the contract.
Phase 7
Commissioning and performance test
Typical duration: 3–6 weeks · Sequential — the last phase before acceptance
- —Dry run, water run and first production on each product
- —Capacity test at the contract tonnes per hour per product
- —Pellet durability, water stability or mixing CV test by the agreed method
- —Energy consumption per tonne recorded at guaranteed capacity
Schedule risk: A performance test without a named product, named method and named acceptance figure is not enforceable. Define it before the order, not at start-up.
Phase 8
Training, handover and warranty
Typical duration: 2–4 weeks · Overlaps commissioning
- —Operator, maintenance and laboratory training
- —As-built drawings, manuals, spare parts list and lubrication plan
- —Punch list closure and provisional acceptance certificate
- —Warranty start date, response times and spare parts availability
Schedule risk: The warranty start date is a commercial term: tie it to provisional acceptance, not to shipment.
Common questions
How long does a turnkey feed mill project take?
From signed contract to handover, a turnkey feed mill project is typically planned over roughly 12 to 18 months, because engineering runs first, civil works and equipment manufacturing run in parallel, and installation, automation and commissioning follow in sequence. The actual duration depends on the product range, ground conditions, permits, import clearance and long-lead items, so treat any generic figure as a planning aid to be confirmed by the supplier's own schedule.
What is the critical path of a feed mill project?
Engineering, then whichever of civil works or long-lead equipment manufacturing finishes last, then mechanical and electrical installation, automation loop checks and finally commissioning and the performance test. Civil works and manufacturing overlap, so the critical path usually runs through detailed engineering and the longest-lead machine.
Can civil works and equipment manufacturing run at the same time?
Yes, and on almost every project they must. Civil works can only start once foundation drawings are released from detailed engineering, and manufacturing starts from the same released engineering, so both phases run in parallel and converge at installation.
When does automation work start?
Software configuration can start during manufacturing, but loop checks, weighing calibration and interlock testing need the cabling and field instruments in place. Plan automation as a phase that overlaps installation and completes before commissioning.
Does FeedMatch build or install feed mills?
No. FeedMatch Group is an independent, supplier-neutral procurement platform. It does not manufacture, install, commission or finance equipment. Every schedule here is a planning aid, and every request is reviewed by a person before any supplier introduction.
Durations on this page are planning ranges for scheduling discussions, not commitments. FeedMatch Group is an independent, supplier-neutral procurement platform: it does not manufacture, install, commission or finance equipment, and every request is reviewed by a person before any supplier introduction.