FinancingFeed working capital, export credit, trade finance & asset leasing — explore options
Reference Delivery

60,000 t/year poultry feed mill — planning tool to contracted scope

Documented walkthrough of how a commercial poultry producer used the FeedMatch capacity calculator and RFQ planner to turn an annual tonnage target into an effective capacity, a written requirement and six quotations that could finally be compared line by line. Figures are the worked example produced by the published tools, not a client disclosure.

Europe
Country
Broilers and layers
Category
60,000 t/year compound feed
Scale
3
Reference outcomes

Load requirements

Design loads used to size housing, utilities and equipment.

Annual tonnage
60,000 t/year
Operating pattern
2 shifts × 8 h × 300 days
Line utilisation assumed
80% (changeovers, cleaning, packing stops)
Effective capacity required
15.63 t/h
Nameplate capacity quoted
17.36 t/h (10% headroom)
Raw-material cover
21 days ≈ 4,200 t of silo and warehouse capacity

System design choices

Why each subsystem was specified the way it was.

AreaChoiceRationale
Process routeGrinding, dosing on load cells, batch mixing, conditioning, pelleting, cooling and crumblingPoultry starter, grower and finisher in pellet and crumble form; no extrusion requirement in the product list.
Capacity basisEffective t/h from annual tonnage, quoted with 10% nameplate headroomA nameplate figure alone hides recipe changeovers and cleaning; the headroom keeps the annual plan achievable.
Storage and handlingIntake, pre-cleaning, 21 days raw-material cover, finished bins, bagging plus bulk loadoutDaily throughput of 200 t sets intake and despatch rates; handling, not the pellet mill, is the usual bottleneck.
AutomationSemi-automatic batching with recipe management and batch reportingCustomer audits required batch records; full traceability scope was priced as a defined option rather than assumed.
Scope splitProcess package from the manufacturer; civil works and building locally; erection supervisedStated in the RFQ so every offer excluded the same items and the comparison stayed like for like.

Results

Representative KPIs achieved on projects of this scope.

Quotations received on one written basis
6
Requirement definition to shortlist
About 10 weeks
Scope items clarified before contract
Boiler, civil works, erection, spares, acceptance test

Challenges and how they were resolved

What went wrong in the first definition of the requirement, and what changed before suppliers quoted.

The first brief only stated an annual tonnage

Manufacturers each assumed their own shifts, days and utilisation, so quoted line sizes differed by more than 40%.

ResolutionThe capacity calculator fixed shifts, days and utilisation in writing, and the RFQ quoted one nameplate figure.

Steam and boiler scope was missing

Two offers included a boiler, three excluded it and one referenced it without a capacity, making price comparison meaningless.

ResolutionThe RFQ checklist made steam source and boiler capacity an explicit in-scope or out-of-scope line for every supplier.

Erection and commissioning were quoted differently

Supervision-only and full mechanical-plus-electrical erection were being compared as if they were the same service.

ResolutionThe request separated supervision, full erection, commissioning, training and warranty into priced line items.

Performance criteria had no acceptance test

Capacity, kWh per tonne, pellet durability and mixing CV were mentioned but never tied to a test method or sign-off.

ResolutionGuarantees and the acceptance test method were written into the RFQ before contract discussions started.

The numbers

Indicative capital and operating figures for a project of this scope. Ranges, not quotations.

Process equipment35–50% of installed cost
Storage and material handling10–18%
Civil works and structure15–25%
Contingency carried5–10%

Representative outcomes

  • Annual target converted to 15.4 t/h effective and 17.1 t/h nameplate capacity
  • One written requirement issued to six manufacturers instead of six different briefs
  • Scope gaps (civil works, steam, erection, spares) priced before contract, not after

Run these numbers yourself

Note: This case study is an anonymized reference scenario. Specific client identities, contract values and commercial terms are withheld under NDA. Figures reflect typical outcomes for projects of this scope and are not a guarantee for your project.

Get a Free QuoteExplore Financing