FinancingFeed working capital, export credit, trade finance & asset leasing — explore options

Feed mill planning tool

Feed Production Cost Per Ton Calculator

Calculate total feed cost per tonne from raw material, electricity, labour, maintenance, packaging, additives and depreciation — then see which input moves your cost most.

How much does it cost to produce one tonne of animal feed?

Total cost per tonne is the raw-material cost of the formula plus the conversion cost of running the plant. Ingredients normally account for 70 to 85 percent of the total. Conversion cost — electricity, labour, maintenance, packaging, depreciation and overhead — commonly falls between USD 9 and USD 30 per tonne, driven far more by utilisation than by any single line item, because fixed costs are spread over whatever tonnage the plant actually produces.

Reviewed August 2026. Planning estimate — not a quotation.

Run the numbers

Variable cost

Weighted delivered cost of the finished ration.

Enter 0 for pure bulk loadout.

Fixed cost
Throughput

Share of scheduled capacity genuinely produced.

Result

Total cost per tonne
USD 379.02
Cost per kilogram
USD 0.379
Conversion cost per tonne
USD 39.02

10.3% of total

Raw-material share
89.7%
Actual annual production
56,160 t
Annual production cost
USD 21,285,603
Fixed cost carried per tonne
USD 26.00

Cost breakdown and sensitivity

ItemUSD/tShare of total
Raw materialUSD 340.0089.7%
ElectricityUSD 3.520.9%
Additives / premixUSD 6.001.6%
PackagingUSD 3.500.9%
LabourUSD 7.482.0%
Maintenance & sparesUSD 4.631.2%
DepreciationUSD 10.682.8%
OverheadUSD 3.210.8%
Sensitivity — Raw material +10%+USD 34.00/t+8.97%
Sensitivity — Utilisation +10% (relative)USD -2.36/t-0.62%
Sensitivity — Labour +10%+USD 0.75/t+0.20%
Sensitivity — Maintenance +10%+USD 0.46/t+0.12%
Sensitivity — Electricity tariff +10%+USD 0.35/t+0.09%
Sensitivity — Specific energy +10%+USD 0.35/t+0.09%

Your inputs travel with the request so you never retype them. Nothing is sent until you review and submit the RFQ yourself.

What this tool calculates

  • Splits cost per tonne into raw material and conversion cost, with the full line-item breakdown and each item's share.
  • Applies your real utilisation so fixed costs land on actual tonnes, not nameplate tonnes.
  • Runs a sensitivity pass showing what happens to cost per tonne when each major input moves 10 percent.
  • Reports cost per kilogram and total annual production cost.
  • Ranks the inputs by influence so you know where negotiation or investment actually pays.

What it cannot do

  • It does not formulate the ration or check nutritional adequacy — it costs the formula you enter.
  • It does not source ingredient prices; you supply the delivered price you actually pay.
  • It excludes distribution to farm, financing cost and taxation.
  • It is not a management-accounting system and will not reconcile to audited statements.

Who this is for

  • Feed manufacturers benchmarking their own conversion cost
  • Integrators deciding between buying compound feed and producing in-house
  • Investors testing whether a planned plant is viable at realistic utilisation
  • Procurement teams challenging a toll-milling or supply quotation

Input definitions

Raw-material cost of the formula (USD/t)
Weighted delivered cost of the finished ration.
Electricity consumption (kWh/t)
Entered by you. Default used for the worked example: 32 kWh/t.
Electricity tariff (USD/kWh)
Entered by you. Default used for the worked example: 0.11 USD/kWh.
Additives / premix not in raw material (USD/t)
Entered by you. Default used for the worked example: 6 USD/t.
Packaging (USD/t)
Enter 0 for pure bulk loadout.
Annual labour cost (USD/yr)
Entered by you. Default used for the worked example: 420000 USD/yr.
Annual maintenance & spare parts (USD/yr)
Entered by you. Default used for the worked example: 260000 USD/yr.
Annual overhead (USD/yr)
Entered by you. Default used for the worked example: 180000 USD/yr.
Depreciable CAPEX (USD)
Entered by you. Default used for the worked example: 9000000 USD.
Depreciation period (years)
Entered by you. Default used for the worked example: 15 years.
Rated throughput (t/h)
Entered by you. Default used for the worked example: 15 t/h.
Operating hours per day (h)
Entered by you. Default used for the worked example: 16 h.
Operating days per year (d)
Entered by you. Default used for the worked example: 300 d.
Utilisation (%)
Share of scheduled capacity genuinely produced.

Methodology

Fixed annual cost (labour, maintenance, depreciation, overhead) is divided by actual annual tonnage, where actual tonnage = rated t/h × hours per day × days per year × utilisation. Variable costs (electricity, packaging, additives) are applied per tonne directly. Total cost per tonne = raw material + variable conversion + fixed conversion. Sensitivity is run by increasing each input 10 percent in isolation and recording the change in total cost per tonne.

Assumptions

  • Raw-material cost is entered as the weighted delivered cost of the finished formula, including shrinkage.
  • Electricity is entered as specific consumption in kWh per tonne multiplied by tariff, covering the whole plant.
  • Depreciation is straight-line over the entered asset life with no residual value.
  • Overhead covers administration, insurance, laboratory and site costs not captured elsewhere.
  • No allowance is made for waste beyond the shrinkage embedded in your raw-material figure.

How FeedMatch builds and reviews its calculators

Worked example — 15 t/h broiler pellet plant

Inputs

  • Raw material USD 340/t, electricity 32 kWh/t at USD 0.11/kWh, additives USD 6/t, packaging USD 3.50/t
  • Labour USD 420,000/year, maintenance USD 260,000/year, overhead USD 180,000/year
  • CAPEX USD 9,000,000 over 15 years, 15 t/h, 16 h/day, 300 days, 78 percent utilisation

Outputs

  • Actual production about 56,160 t/year
  • Conversion cost about USD 34/t
  • Total cost about USD 374/t, or USD 0.374/kg
  • Raw material is roughly 91 percent of total cost

How to read it. A 10 percent raw-material move shifts total cost by about USD 34 per tonne. A 10 percent electricity move shifts it by about USD 0.35. That is the whole argument for spending negotiating effort on ingredient contracts before energy contracts — but note that conversion cost is where a badly utilised plant bleeds, since utilisation falling from 78 to 60 percent adds roughly USD 8 per tonne on its own.

Limitations

  • Conversion cost varies widely by country, capacity and product mix. Use your own figures rather than the defaults for any decision.
  • Sensitivity is one-at-a-time; real markets move several inputs together, and correlated moves can be larger than the sum shown here.
  • Ranges are planning estimates for budgeting, not quotations or guarantees.

All figures are indicative planning estimates for budgeting and supplier discussion. They are not quotations, guarantees or professional engineering, nutritional, legal or financial advice. Have results reviewed by the responsible professionals before you commit capital.

Frequently asked questions

What is the biggest cost in animal feed production?
Raw materials, by a wide margin — typically 70 to 85 percent of total cost per tonne, and often above 90 percent for simple poultry rations in grain-producing countries. Within conversion cost, the largest items are usually labour and depreciation rather than energy, although energy rises sharply in extrusion plants and in markets with high tariffs.
What is a normal conversion cost for a feed mill?
As an indicative planning band, USD 9 to USD 30 per tonne covers most compound-feed plants. Large, highly utilised bulk plants in low-tariff countries sit at the bottom; small, bagged, part-utilised plants sit at the top or above it. Extruded aquafeed and pet food run considerably higher because of drying energy and packaging. Treat any single published figure with suspicion unless it states capacity, utilisation, product and country.
How does utilisation change cost per tonne?
Fixed costs do not fall when the plant runs less. A plant with USD 1.5 million of annual fixed cost producing 56,000 tonnes carries about USD 27 per tonne; the same plant producing 40,000 tonnes carries about USD 38. That USD 11 swing usually dwarfs anything achievable through energy efficiency, which is why order book and reliability matter more to unit cost than equipment brand.
Should I include depreciation in cost per tonne?
Include it for investment decisions, plant comparisons and make-or-buy analysis, because the asset is genuinely consumed. Exclude it when you are deciding whether to accept an incremental order in an existing plant, since that decision only turns on cash costs. This calculator shows depreciation as a separate line so you can read the number both ways.

Equipment and market context

Turn the result into comparable quotations

FeedMatch Group is a supplier-neutral B2B procurement platform. Describe the requirement once and we qualify relevant manufacturers and suppliers, normalise offers to the same battery limits and guarantees, and return a like-for-like comparison. FeedMatch does not manufacture feed or feed-mill machinery.

RFQ checklist
Get a Free QuoteExplore Financing